Question: Another term for activity on node, the most commonly used technique for constructing a schedule model, is: a. precedence diagramming method (PDM) b. arrow diagramming

Another term for “activity on node,” the most commonly used technique for constructing a schedule model, is:

a. precedence diagramming method (PDM)

b. arrow diagramming method (ADM)

c. activity on arrow (AOA)

d. activity attribute method (AAM)

Step by Step Solution

3.42 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Another term for activity on node the most commonly used technique for constructing a schedule mode... View full answer