Question: Another term for activity on node, the most commonly used technique for constructing a schedule model, is: a. precedence diagramming method (PDM) b. arrow diagramming
Another term for “activity on node,” the most commonly used technique for constructing a schedule model, is:
a. precedence diagramming method (PDM)
b. arrow diagramming method (ADM)
c. activity on arrow (AOA)
d. activity attribute method (AAM)