Ellen is estimating how much it will cost to recarpet the executive conference room. After selecting the

Question:

Ellen is estimating how much it will cost to recarpet the executive conference room. After selecting the grade and pattern of carpet, Ellen multiplies the carpet price per square yard times the number of square yards in the conference room to derive the total price of the material. This estimating method is called _____________.

a. expert judgment

b. analogous estimating

c. parametric estimating

d. three-point estimating