The budget within the cost baseline that is allocated for identified risks, for which mitigating responses are
Question:
The budget within the cost baseline that is allocated for identified risks, for which mitigating responses are developed, is called the _____________.
a. contingency reserve
b. management reserve
c. control account
d. activity cost estimate
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Contemporary Project Management
ISBN: 9780357715734
5th Edition
Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells
Question Posted: