The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs

Question:

The “process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs” is referred to as:

a. determine budget

b. estimate costs

c. plan cost management

d. control costs