Suppose your AC for the project was $100,000 and your EV was $78,000. What is the value

Question:

Suppose your AC for the project was $100,000 and your EV was

$78,000. What is the value of your project’s CPI?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost And Value Management In Projects

ISBN: 9781119933540

2nd Edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: