Question: A project manager presented earned value analysis data in a tabular format in a performance report. Another way the project manager could have presented the

A project manager presented earned value analysis data in a tabular format in a performance report. Another way the project manager could have presented the earned value analysis data is with:

A linear graph An S-curve A logarithmic curve An Epsilon graph