Question: A project manager presented Earned value analysis data in a tabular format while providing a performance report. An alternative way in which the project manager


A project manager presented Earned value analysis data in a tabular format while providing a performance report. An alternative way in which the project manager could have presented the Earned value analysis data is by using:

A. A linear graph B. An S-curve C. A logarithmic curve D. An Epsilon graph