Question: Andrew is managing a construction project. He is using his communication, interpersonal and management skills to keep the key project stakeholders engaged with the project.

Andrew is managing a construction project. He is using his communication, interpersonal and management skills to keep the key project stakeholders engaged with the project. Which of the following activities is not related to the Manage Stakeholder Engagement process?

Addressing and resolving issues Developing the stakeholder engagement plan Confirming the stakeholders' continued commitment Negotiating and communicating with the stakeholders