Question: The performance reports produced during the Control Procurements process are then provided to which project management process for further processing? Monitor & Control Project Work
The performance reports produced during the Control Procurements process are then provided to which project management process for further processing?
Monitor & Control Project Work in the form of work performance information Direct & Manage Project Work in the form of work performance data Perform Integrated Change Control in the form of a change request Performance report is not an output of the Control Procurement process