Question: The performance reports produced during the Control Procurements process are then provided to which project management process for further processing? A. * Monitor & Control
The performance reports produced during the Control Procurements process are then provided to which project management process for further processing?
A. * Monitor & Control Project Work in the form of work performance information B. Direct & Manage Project Work in the form of work performance data C. Perform Integrated Change Control in the form of a change request D. Performance report is not an output of the Control Procurement process