Question: What is a recommended method for controlling change within a project? Have only the project manager able to initiate change. Have each change approved or
What is a recommended method for controlling change within a project?
Have only the project manager able to initiate change.
Have each change approved or rejected through a formal change control process.
Allow each project member ultimate control of changes within their realm of the project without a review process.
Freeze scope and allow absolutely no changes.