Question: Draw the AON project network using the following information: How long would it take to complete this project? Which activities are included on the critical

Draw the AON project network using the following information:

ACTIVITY IMMEDIATE PREDECESSOR (S) DURATION (WEEKS) A 4 B 35 UD LLI

How long would it take to complete this project? Which activities are included on the critical path?

ACTIVITY IMMEDIATE PREDECESSOR (S) DURATION (WEEKS) A 4 B 35 UD LLI 5 A 9 E B 3 F C, E 1 G D 2 H F 3 I G, H 15 J G 1