Question: Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) net- work diagram. a) Which activities are on the
Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) net- work diagram.
a) Which activities are on the critical path?
b) What is the length of the critical path? Activity ABCDEFGH I Immediate Predecessor(s) Time (days) A 52 2 A 4 B 5 B 5 S E, F 2 D G, H 3 5