Question: Question 1 0.4 pts Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network diagram. IMMEDIATE ACTIVITY TIME

Question 1 0.4 pts Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network diagram. IMMEDIATE ACTIVITY TIME (DAYS) PREDECESSOR(S) A 1 B D ANU A B B U W N U U U E, F H D - G, H a) The activities on the critical path are Insert the path in the following format X-X-X-X-X-X using capital letters. b) The length of the critical path is days. Insert the length of the critical path as a whole number
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
