Question: 3 . 6 Given the activities whose sequence is described by the following table, draw the appropriate activity - on - arrow ( AOA )

3.6 Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network diagram.
a. Which activities are on the critical path?
b. What is the length of the critical path?
\table[[ACTIVITY,IMMEDIATE,TIME (DAYS)],[A,-,5],[B,A,2],[C,A,4],[D,B,5],[E,B,5],[F,C,5],[G,E, F,2]]