Question: Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network diagram. (a) Which activities are on the critical
(a) Which activities are on the critical path?
(b) What is the length of the criticalpath?
.png)
Irmmediate Predecessor(s) Time (days) Activity E, F G, H
Step by Step Solution
3.37 Rating (169 Votes )
There are 3 Steps involved in it
a b Critical path ... View full answer