If you add three more people to a project team of five, how many more communication channels
Question:
If you add three more people to a project team of five, how many more communication channels will you add?
a. 2
b. 12
c. 15
d. 18
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (2 reviews)
Answered By
Vineet Kumar Yadav
I am a biotech engineer and cleared jee exam 2 times and also i am a math tutor. topper comunity , chegg India, vedantu doubt expert( solving doubt for iit jee student on the online doubt solving app in live chat with student)
5.00+
2+ Reviews
10+ Question Solved
Related Book For
Question Posted:
Students also viewed these Business questions
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
Your advertising agency has been hired to design and develop a marketing communication plan to the organisation you analysed. The Organisation that I have analysed is Samsung: In the paper, I...
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
Give the approximate temperature at which creep deformation becomes an important consideration for each of the following metals: nickel, copper, iron, tungsten, lead, and aluminum.
-
Show that the Associative Property holds for compositions of functions-that is, (f o (g o h)) (x) = {(f o g) o h} (x).
-
1. Using only financial criteria to evaluate projects that enhance employee safety or reduce detrimental environmental impact 2. Changing assumptions or estimates for projects solely so that they...
-
Sports-Related Concussions in Kids Researchers examined all sports-related concussions reported to an emergency room for children ages 5 to 18 in the United States over the course of one year. Table...
-
a. What percentage of the waybills constituted the sample? b. What percentage error was made by using the sample to estimate the total revenue due C&O? c. At the time of the study, the cost of a...
-
If det [a b] = c d 2 -2 0 a. det c+1 -1 2a d-2 2 2b -2 calculate:
-
Which of the following is not a guideline to help improve time spent at meetings? a. Determine if a meeting can be avoided. b. Invite extra people who support your project to make the meeting run...
-
What strategy can a project manager use to deliver bad news? a. Tell a joke first. b. Tell senior management as soon as possible so they can develop alternatives and recommendations. c. Ask the...
-
If the objectives of the federal tax system are multi faceted and include raising revenues, providing investment incentives, encouraging certain industries, and meeting desired social objectives, is...
-
4.Today ist= 0. You have just bought a five-year zero-coupon Treasury bond with $1,000 face value. You paid $950. (a)What is the annually compounded yield to maturity on the bond? (b)Suppose that...
-
What do you think explains the gender double standard regarding young people's sexuality that exists in so many cultures? What are some examples from your culture?
-
a) Assuming that daily Non-Fungible Token (NFT)price movements are normally distributed, with a mean return of 0.19% and a standard deviation of 1.95%, calculate the following: i)The probability that...
-
Would the following events usually lead to capital deepening? Answer yes or no for parts a., b., and c. below. a. A decrease in international trade due to shutdowns from a global pandemic. b. A trend...
-
1.what is a budget. How does a budget contribute to good Management. (2). Jane Gilligan ask your help in understanding the essential of effective budgeting. Identify the essential of Jane. (3). Lori...
-
Suppose Johnson & Johnson and the Walgreen Company have the expected returns and volatilities shown below, with a correlation of 22%. For a portfolio that is equally invested in Johnson & Johnsons...
-
Solve for the equilibria of the following discrete-time dynamical systems Pr pt+1 = Pr+2.0(I-Pr)
-
Why do you think schedule issues often cause the most conflicts on projects?
-
Explain the difference between activity duration estimating and estimating the effort required to perform an activity.
-
Explain the following schedule development tools and concepts: Gantt charts, critical path method, PERT, and critical chain scheduling.
-
1, How many quarts can be measured from 2 1/2 kilograms of honey? 2, If a recipe calls for 2 gallons of fresh hulled strawberries, how many pounds should we use? 3, How many tablespoons are in 1...
-
Course: ACCT 253 Ly Case Study 4 (Part 2) - Lyryx Learning Inc - Google Chrome lifa1.lyryx.com/student-servlets/CaseStudyServlet?ccid=10460 C lifa1.lyryx Part 2 [20 points] Tyryx purse Home SunBlush...
-
The following worksheet is called a Balance Sheet Equation Worksheet. The worksheet lists the key events in the life of UWP over years 1 through 3: each of these events is likely to affect the...
Study smarter with the SolutionInn App