Question: ______ is a network diagramming technique used to predict total project duration. a. PERT b. A Gantt chart c. Critical path method d. Crashing

______ is a network diagramming technique used to predict total project duration.

a. PERT

b. A Gantt chart

c. Critical path method

d. Crashing

Step by Step Solution

3.51 Rating (154 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

c Cr... View full answer