Question: Create a precedence diagram based on the following information: There are ten total tasks, named AJ. Tasks A, B, and H have durations
Create a precedence diagram based on the following information:
• There are ten total tasks, named A–J.
• Tasks A, B, and H have durations of two days.
• Tasks C, E, I, and J have durations of three days.
• Tasks D, F, and G have durations of one day.
• Tasks A, B, and D can be conducted in parallel.
• Task C must precede task B.
• Tasks A and F must precede Task E.
• Task E must precede Task G.
• Tasks B and D must precede Tasks H and I, respectively.
• Tasks G, H, and I may be conducted in parallel.
• Tasks G, H, and I precede Task J.