Question: Using any software, draw a precedence diagram based on the following information ( the precede here means immediate precede ) : There are ten total
Using any software, draw a precedence diagram based on the following information the precede here means immediate precede:
There are ten total tasks, named AJ
Tasks A B and H have durations of two days.
Tasks C E I, and J have durations of three days.
Tasks D F and G have durations of one day.
Tasks A B and D can be conducted in parallel.
Tasks A and F can be conducted in parallel.
Tasks A and F must precede Task E
Task E must precede Task G
Task C must precede task B
Task B must precede Task H
Task D must precede Task I.
Tasks G H and I may be conducted in parallel.
Tasks G H and I precede Task J
Create an arrow diagram with the information from question
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock