Question: Using any software, create a precedence diagram based on the following information: There are ten total tasks, named AJ. Tasks A, B, and H have
Using any software, create a precedence diagram based on the following information:
There are ten total tasks, named AJ.
Tasks A, B, and H have durations of two days.
Tasks C, E, I, and J have durations of three days.
Tasks D, F, and G have durations of one day.
Tasks A, B, and D can be conducted in parallel.
Task C must precede task B.
Tasks A and F must precede Task E.
Task E must precede Task G.
Tasks B and D must precede Tasks H and I, respectively.
Tasks G, H, and I may be conducted in parallel.
Tasks G, H, and I precede Task J.