Question: Using any software, create a precedence diagram based on the following information: There are ten total tasks, named AJ. Tasks A, B, and H have

Using any software, create a precedence diagram based on the following information:

There are ten total tasks, named AJ.

Tasks A, B, and H have durations of two days.

Tasks C, E, I, and J have durations of three days.

Tasks D, F, and G have durations of one day.

Tasks A, B, and D can be conducted in parallel.

Task C must precede task B.

Tasks A and F must precede Task E.

Task E must precede Task G.

Tasks B and D must precede Tasks H and I, respectively.

Tasks G, H, and I may be conducted in parallel.

Tasks G, H, and I precede Task J.