Question: Using any software, draw a precedence diagram based on the following information (the precede here means immediate precede): There are ten total tasks, named AJ.
- Using any software, draw a precedence diagram based on the following information (the precede here means immediate precede):
- There are ten total tasks, named AJ.
- Tasks A, B, and H have durations of two days.
- Tasks C, E, I, and J have durations of three days.
- Tasks D, F, and G have durations of one day.
- Tasks A, B, and D can be conducted in parallel.
- Tasks A and F can be conducted in parallel.
- Tasks A and F must precede Task E.
- Task E must precede Task G.
- Task C must precede task B.
- Task B must precede Task H.
- Task D must precede Task I.
- Tasks G, H, and I may be conducted in parallel.
- Tasks G, H, and I precede Task J.
2. Create an arrow diagram with the information from question
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock