Question: Creating the work breakdown structure is a vital step for the project team for a number of reasons. 3 of the following statements describe a

Creating the work breakdown structure is a vital step for the project team for a number of reasons. 3 of the following statements describe a purpose or result of creating the WBS. Find the statement that does not.

A. To make the work more manageable.

B. To create a task-oriented decomposition of the work.

C. To create a more refined description of the deliverables at a lower level than the scope statement.

D. To define work packages that can be assigned, monitored, and controlled.