Question: Mark has a project where task A is dependent on the start and has a duration of 3. Task B is dependent on start and

Mark has a project where task A is dependent on the start and has a duration of 3.

Task B is dependent on start and has a duration of 5.

Task C is dependent on A and has a duration of 4.

Task D is dependent on B and has a duration of 6, and the finish is dependent on tasks C and D. Mark is using his project network diagram to help create a schedule. The schedule for the project is usually created during which process?

A. Estimate Costs.

B. Determine Budget.

C. Control Schedule.

D. Develop Schedule.