Question: Consider the data about project activities given in the table below. a. Schedule the work in such a way that each person always has only
Consider the data about project activities given in the table below.
a. Schedule the work in such a way that each person always has only one task to perform (do not reduce the durations of activities or insert buffers as yet).
b. Indicate the critical chain.
c. Indicate where the feeding buffers should be inserted.
d. What is the difference in the lengths of the critical path and the critical chain?
Activity Predecessor(s) Duration (Days) Resources A B A C D C E D. J F E, B G F H 2 3 3232 24 John Sue Sue & John Sue & Al John Ann Sue J H 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
