Question: If BAC for a work package is $10,000 and BCWP = $4,000, then the work package is percent complete. a. 40 b. 80 c. 100

If BAC for a work package is $10,000 and BCWP = $4,000, then the work package is percent complete.

a. 40

b. 80

c. 100

d. 120