Question: A project consists of five activities. The start time and duration of each activity are given below. Summarize this data in a Gantt chart. Activity

A project consists of five activities. The start time and duration of each activity are given below. Summarize this data in a Gantt chart.


Activity A B C D E Start time 0 3 in 5

Activity A B C D E Start time 0 3 in 5 6 3 Duration 4 6 7 8 6

Step by Step Solution

3.48 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Here is the Gantt chart for the given data Activity A B C D E Start Ti... View full answer