Question: After creating the work breakdown structure (WBS), Oswin is estimating the overall project duration by totaling the estimates of all the lower-level components. What estimating

After creating the work breakdown structure (WBS), Oswin is estimating the overall project duration by totaling the estimates of all the lower-level components. What estimating technique is Oswin using?

a. Three-point

b. Parametric

c. Analogous d.Bottom-up