Question: After creating the work breakdown structure (WBS), Oswin is estimating the overall project duration by totaling the estimates of all the lower-level components. What estimating
After creating the work breakdown structure (WBS), Oswin is estimating the overall project duration by totaling the estimates of all the lower-level components. What estimating technique is Oswin using?
a. Three-point
b. Parametric
c. Analogous d.Bottom-up