Question: Koda, your project manager, is working to decompose the elements of the project into logical and manageable portions so that you can begin creating the
Koda, your project manager, is working to decompose the elements of the project into logical and manageable portions so that you can begin creating the requirements traceability matrix. Once complete, what will she have created?
a. The project management plan
b. The details of all project and product work
c. An outline of the requirements traceability matrix d.The scope baseline