Question: Given the activities data in the table below: (a) Draw the network. (b) Find the critical path. (c) Find the slacks on all activities. Activity
Given the activities data in the table below:

(a) Draw the network.
(b) Find the critical path.
(c) Find the slacks on all activities.
Activity ABCDEFI- G H I Times (weeks) 3 6 8 7 5 10 4 5 6 Preceding activities | |ABCu D, E, F G
Step by Step Solution
★★★★★
3.39 Rating (155 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
The task at hand involves project management concepts specifically network diagrams critical paths and slack time Well address each part of the question but please be aware that I cannot draw the netw... View full answer