Question: The following information has been computed from a project: Expected total project time = T = 62 weeks Project variance ( 2 p ) =
The following information has been computed from a project:
Expected total project time = T = 62 weeks
Project variance (σ2p) = 81
What is the probability that the project will be completed 18 weeks before its expected completion date?