The following table shows jobs to be processed at a machine. Determine the processing sequence that will

Question:

The following table shows jobs to be processed at a machine. Determine the processing sequence that will minimize total number of late jobs.

Processing Time Due Date Job (days) (days) A 3 4 5 5 10 D 2 11 E 4 13 20