Question: Using the product structure for Alpha in Solved Problem 14.1, and the following lead times, quantity on hand, and master production schedule, prepare a net
Using the product structure for Alpha in Solved Problem 14.1, and the following lead times, quantity on hand, and master production schedule, prepare a net MRP table for Alphas.
Data From Problem 14.1
Determine the low-level coding and the quantity of each component necessary to produce 10 units of an assembly we will call Alpha. The product structure and quantities of each component needed for each assembly are noted in parentheses.



B(1) Alpha C(1) D(2) C(2) E(1) F(1) E(1) F(1)
Step by Step Solution
3.49 Rating (149 Votes )
There are 3 Steps involved in it
Problem Analysis and Assumptions To create a Net Material Requirements Planning MRP table for Alpha we need to consider the following 1 Product Structure Alpha requires B1 and C1 B requires D2 and C2 ... View full answer