Question: Using the product structure for Alpha in Solved Problem 14.1, and the following lead times, quantity on hand, and master production schedule, prepare a net

Using the product structure for Alpha in Solved Problem 14.1, and the following lead times, quantity on hand, and master production schedule, prepare a net MRP table for Alphas.


Data From Problem 14.1

Determine the low-level coding and the quantity of each component necessary to produce 10 units of an assembly we will call Alpha. The product structure and quantities of each component needed for each assembly are noted in parentheses.

B(1) Alpha C(1) D(2) C(2) E(1) F(1) E(1) F(1)


image text in transcribed

image text in transcribed



B(1) Alpha C(1) D(2) C(2) E(1) F(1) E(1) F(1)

Step by Step Solution

3.49 Rating (149 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Problem Analysis and Assumptions To create a Net Material Requirements Planning MRP table for Alpha we need to consider the following 1 Product Structure Alpha requires B1 and C1 B requires D2 and C2 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management 6th Questions!