A company using a Kanban system has an inefficient machine group. For example, the daily demand for
Question:
A company using a Kanban system has an inefficient machine group. For example, the daily demand for part L105A is 3,000 units. The average waiting time for a container of parts is 0.8 day. The processing time for a container of L105A is 0.2 day, and a container holds 270 units. Currently, 20 containers are used for this item.
a. What is the value of the policy variable, a?
b. What is the total planned inventory (work-in-process and finished goods) for item L105A?
c. Suppose that the policy variable, a, was 0. How many containers would be needed now? What is the effect of the policy variable in this example?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management Processes And Supply Chains
ISBN: 9781292409863
13th Global Edition
Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman
Question Posted: