Question: A company using a kanban system has an inefficient machine group. For example, the daily demand for part L 1 0 5 A is 3

A company using a kanban system has an inefficient
machine group. For example, the daily
demand for part L105A is 3,000 units. The average waiting
time for a container of parts is 0.8
day. The processing time for a container of L105A is 0.2 day,
and a container holds 280 units.
Currently, 29 containers are used for this item. What is the
total planned inventory (WIP and
finished) for L105A?
8102 units
5400 units
8120 units
5410 units