Question: A project network has two paths running through it. The first path has an expected length of 10 days and a variance of 2 days.
A project network has two paths running through it. The first path has an expected length of 10 days and a variance of 2 days. The second path has an expected length of 11 days and a variance of 1 day. What is the probability that this project will require more than 14 days to complete?
Step by Step Solution
3.47 Rating (160 Votes )
There are 3 Steps involved in it
To find the probability that the project will require more than 14 days to complete we need to consi... View full answer