Question: A project network has two paths running through it. The first path has an expected length of 15 days and a variance of 4 days.

A project network has two paths running through
A project network has two paths running through it. The first path has an expected length of 15 days and a variance of 4 days. The second path has an expected length of 12 days and a variance of 4 days. What is the probability that this project can be completed in 16 days? TTTT Paragraph 3 (12pt) ET %DOO TT. Arial lala 1111 ilil NITI Ilm