Question: Consider the playkool storage studio below. We wish to design an assembly line to assemble several units. The assembly takes and their standard times (in

Consider the playkool storage studio below. We wish to design an assembly line to assemble several units. The assembly takes and their standard times (in second) are listed below.

Consider the playkool storage studio below. We wish to design an assembly

The parts are to be assembled according to the following precedence network:

line to assemble several units. The assembly takes and their standard times

a. Calculate the cycle time if 75 units per hour are to be assembled.
b. What is the minimum number of workstations?
c. Using your answer to part a, perform assembly-line balancing using “Assign the task with the longer time” heuristic rule, breaking any ties using “Assign the task with the most followers” rule. If there is still a tie, break it randomly.

(in second) are listed below.The parts are to be assembled according to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a CT 60 minutes 75 8 minute 48seconds b N min Total time for oneitem C... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Management Leadership Questions!