Question: To assemble the plastic chair (shown below using an assembly line, the following activities with estimated standard times are required. a. Draw a precedence for
To assemble the plastic chair (shown below using an assembly line, the following activities with estimated standard times are required.
.png)
a. Draw a precedence for this assembly.
b. If the desired output rate of the assembly line is 120 chaires per hour, what is the minimum number of workstations required?
c. Using a cycle time of 30 second per chair, and Assign the task with the longest time” heuristic rule, design the assembly line (i,e., balance the line).
Step by Step Solution
There are 3 Steps involved in it
a Precedencenetwork b CT 3600 120 30 sec per unit N min ... View full answer