Question: A production process at Kenneth Day Manufacturing is shown in figure S7.9. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding
A production process at Kenneth Day Manufacturing is shown in figure S7.9. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding operations.
.png)
A product needs to go through only one of the three assembly operations (the operations are in parallel).
(a) Which operation is the bottleneck?
(b) What is the process time of the overall system?
(c) What is the process cycle time of the overall system?
(d) If the firm operates 8 hours per day, 20 days per month, what is the monthly capacity of the manufacturingprocess?
Assembly Sawing Sandin 0.7 unitsihr 6 units/hr 6 units/hr Assembly 0.7 unitshr edng 2 units/hr Drilling Assemby 2.4 units/hr 0.7 unitsihr
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
a Converting each capacity to a process time Sawing Sanding 60 minhr 6 ... View full answer