Question: Jobs have different processing times and due dates. If a job is finished earlier than its due date but one day sooner than expected, how
Jobs have different processing times and due dates. If a job is finished earlier than its due date but one day sooner than expected, how does this change the job’s tardiness?
a. Tardiness decreases by one day.
b. Tardiness does not change.
c. Tardiness increases by one day.
d. It is not possible to determine the impact on the tardiness of the job with the given information.
Step by Step Solution
3.32 Rating (170 Votes )
There are 3 Steps involved in it
b Tardiness does not change Tardiness is the difference bet... View full answer