Question: Jobs have different processing times and due dates. If a job is finished earlier than its due date but one day sooner than expected, how
Jobs have different processing times and due dates. If a job is finished earlier than its due date but one day sooner than expected, how does this change the job’s lateness?
a. Lateness decreases by one day.
b. Lateness does not change.
c. Lateness increases by one day.
d. It is not possible to determine the impact on lateness of the job with the given information.
Step by Step Solution
3.34 Rating (166 Votes )
There are 3 Steps involved in it
a Lateness is the difference ... View full answer