Jobs have different processing times and due dates. If a job is finished earlier than its due

Question:

Jobs have different processing times and due dates. If a job is finished earlier than its due date but one day sooner than expected, how does this change the job’s lateness? 

a. Lateness decreases by one day. 

b. Lateness does not change. 

c. Lateness increases by one day. 

d. It is not possible to determine the impact on lateness of the job with the given information.