Question: Marilyn Hart, operations manager at Hart Electronics, faces assembly-line balancing problems. She has been told that the firm needs to complete 1,400 electronic relays per

Marilyn Hart, operations manager at Hart Electronics, faces assembly-line balancing problems. She has been told that the firm needs to complete 1,400 electronic relays per day. There are 420 minutes of productive time in each working day (which is equivalent to 25,200 seconds). Group the assembly-line activities in the following table into appropriate workstations and calculate the efficiency of the balance.

TASK A B C D EF TIME (SECONDS) 13 4 10 10

TASK A B C D EF TIME (SECONDS) 13 4 10 10 62 12 MUST FOLLOW TASK A B D E TASK G H | J K L TIME (SECONDS) 5 5.0 6 7 Ln 5 45 15 MUST FOLLOW TASK E F, G H H 1, J C, K

Step by Step Solution

3.43 Rating (178 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Using Longest Operation Time the res... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!