Question: Marilyn Hart, operations manager at Hart Electronics, faces assembly - line balancing problems. She has been told that the firm needs to complete 1 ,

Marilyn Hart, operations manager at Hart Electronics, faces assembly-line balancing problems. She has been told that the firm needs to complete1,400 electronic relays per day. There are 420 minutes of productive time in each working day(which is equivalent to25,200 seconds). The assembly-line activities are given below:
Task
Time(seconds)
Must Follow Task
Task
Time(seconds)
Must Follow Task
A
13
-
G
5
E
B
4
A
H
6
F, G
C
10
B
I
7
H
D
10
-
J
5
H
E
6
D
K
4
I, J
F
12
E
L
15
C, K
Part 2
Using longest task(operating) time heuristic, group the assembly-line activities into appropriate workstations. Complete the following table.
Station
Tasks
1
A,
B
2
D
, E
3
F,
G
4
H,
C
5
I, J,
K
6
L
Part 3
The actual efficiency of the balance is
enter your response here%(enter your response rounded to one decimal place).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!