Question: 2. (30) Marilyn Hart, operations manager at Hart Electronics, faces assembly-line balancing problems. She has been told that the firm needs to complete 1,400 electronic

2. (30) Marilyn Hart, operations manager at Hart
2. (30) Marilyn Hart, operations manager at Hart Electronics, faces assembly-line balancing problems. She has been told that the firm needs to complete 1,400 electronic relays per day. There are 420 minutes of productive time in each working day. Group the assembly-line activities below into appropriate workstations and calculate the efficiency of the balance. Task Time Must follow Task Time Must follow (seconds) task (seconds) task 13 G 5 E B A 6 F, G 10 B 1 7 D 10 J 5 H E D K 4 F 12 E L 15 CK 6