Question: Given the following task, times, and sequence, develop a balanced line capable of operating with a 10-minute cycle time at Dave Vissers company. a) Draw
Given the following task, times, and sequence, develop a balanced line capable of operating with a 10-minute cycle time at Dave Visser’s company.

a) Draw the precedence diagram.
b) Assign tasks to the minimum feasible number of workstations according to the greatest time remaining (ranked positional weight) decision rule.
c) What is the efficiency of the process?
TASK ELEMENT A B D ELVI TIME (MINUTES) minim min ELEMENT PREDECESSOR A B C B, D D G