Question: The production process at ABC Manufacturing is as shown in the following figure: A product in this production process needs to go through only one
The production process at ABC Manufacturing is as shown in the following figure:

A product in this production process needs to go through only one of the painting operations:
1. Which one of the operations in the previous figure is a bottleneck operation?
2. If Orion Manufacturing operated 8 hours/day, 25 days/month, what is the monthly capacity of the companys production process?
Grinding 7 units/hour Painting 2 units/hour Milling 7 units/hour Painting 2 units/hour Assembly 3 units/hour Shearing 5 units/hour Drilling 6 units/hour Painting 2 units/hour
Step by Step Solution
3.42 Rating (161 Votes )
There are 3 Steps involved in it
1 The bottleneck is ... View full answer