Question: Using the following project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 38 weeks. P(project 38)

Using the following project information
Optimistic Time Expected Activity Most Pessimistic Immediate Variance Likely Predecessor(s) Estimate(weeks) Time Time Ti

The critical path is A-C-E-G-I-J.
(a) Calculate the probability that the project will be completed in 38 weeks.
P(project 38) =
(b) Calculate the probability that the project will be completed in 42 weeks.
P(project 42) =

Optimistic Time Expected Activity Most Pessimistic Immediate Variance Likely Predecessor(s) Estimate(weeks) Time Time Time Estimates (weeks) Estimates (weeks) (weeks) 1.000 6.00 A 9. none B 3 5 A 0.444 5.00 4 12 A. 1.778 7.33 D 8. 10 1.000 7.67 10 16 3.361 10.17 D,E 4 0.111 4.00 D,E 0.694 5.83 6. 10 0.694 6.33 8 11 1.000 8.00 0.000 3.00 3. 6. 3. 4. 3. 3.

Step by Step Solution

3.64 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Path Expected Completion Time Variance 38 week zvalue ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(1175).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!