Using the job information in Problem 3, Construct a Gantt chart using the minimum slack per operation

Question:

Using the job information in Problem 3, Construct a Gantt chart using the minimum slack per operation (MINSOP) rule to determine the job priority ranking at each machine as the jobs progress through the shop. Assume all jobs arrived simultaneously. Determine the makespan , average flowtime , average queue time, average lateness, and average tardiness. Also assume that transfer times are zero.

Data from 3

Due Dates (hrs.) Job Est. Hours A/2, B/1, C/2 A/1, c/3, B/2 15 2 2.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: