You are calculating the estimated time to completion for a project of 15 months duration and a

Question:

You are calculating the estimated time to completion for a project of 15 months€™ duration and a budgeted cost of $350,000. Assuming the following information, calculate the Schedule Performance Index and the estimated time to completion (figures are in thousands of U.S dollars):

Schedule Variances Planned Value (PV) Earned Value (EV) Schedule Performance Index Estimated Cost to Completion 65 58

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto